„Hamburger – Deckel“ Expansion of the A7 motorway

In the course of the expansion of the A7 motorway from the Elbe tunnel to the northern city border, a total of over 3600m of motorway tunnels will be built in 3 sections. Longitudinal ventilation will be installed in all tunnels.
From north to south starting with the
- Tunnel Schnelsen, length 560m - completed end of 2019
- Tunnel Stellingen, length 890m - Completed 2021
- Tunnel Altona, length 2200m (construction period 2022 - 2028)